Applied Materials      



 
Test Plan Products    





"Applied Materials CCS Technology provides the means for doing the right thing when it comes to equipment certification - comprehensive testing against specific requirements, rigorously and consistently applied."

SEMI E30 GEM Test Plan

Type Test Section PDF Documents
Part # 11102
Description CCStests SEMI E30 GEM Unit Test Section is used to verify requirements and scenarios as defined by SEMI® in its Equipment Automation/Software volume for the E30 GEM standard. This test section contains a set of automated, as well
as manual test cases, to create positive and negative test conditions.
Requires CCSenvoy for run-time.
User

Device Manufacturer: Primarily uses CCStests SEMI E30 GEM Test Section for source inspection acceptance tests or as part of delivery audit for SEMI E30 GEM requirements.

Equipment Supplier: Used by the Test Engineer who is responsible for supplier internal system and QA testing of an equipment E30 GEM communication interface. Development Engineers may also utilize this during development integration test phases.

Systems Integrator: A qualified Systems Integrator engineer would use this test section as part of the CCSpartner program for performing CCScertify services or during dry-run and integration tests.

Licensing End-User License Agreement (EULA) required.
Summary CCStests SEMI E30 GEM Unit Test Section contains over 200 automated and 20 manual test cases. These test cases are categorized into over 30 test groups. Report RP-10 Results – GEM Compliance Statement further categorizes the test cases into GEM capabilities producing a report similar to the SEMI. The following are the test groups for the SEMI E30 GEM Test Section.
Group
Outline

Fundamental Requirements



  • Host-Initiated S1,F13/F14 Scenario
  • Control (Operator Initiated)
  • On-Line Identification
  • Error Messages
  • Event Notification


Additional Capabilities



  • Establish Communications
  • Dynamic Event Report Configuration
  • Clock
    • Host Instructs Equipment to Set Date/Time
    • Equipment Requests Host for Date/Time
  • Control (Host-Initiated)
  • Variable Data Collection
  • Status Data Collection
  • Equipment Constants
  • Alarm Management
    • Enable/Disable Alarms
    • List Alarms
    • Alarm Report Send
  • Process Program Management
    • Process Program Directory Request
    • Process Program Change on Equipment
    • Unformatted Process Program
        • Unformatted Host Initiated Process Program
        • Unformatted Equipment Initiated Process Program
    • Formatted Process Program
        • Formatted Host Initiated Process Program
        • Formatted Equipment Initiated Process Program
    • Process Program Delete
  • Equipment Terminal Services
    • Operator Sends Terminal Information
    • Host Sends Terminal Information - Single Block
    • Host Sends Terminal Information – Equip Does NOT Support Multi-Block
    • Host Sends Terminal Information – Equip Supports Multi-Block
  • Trace Data Collection
  • Limits Monitoring
  • Material Movement
  • Remote Control
    • Remote Commands Data Collection
    • Remote Commands Message Scenarios Tests
  • Spooling
    • Spooling Data Collection
    • Spooling Message Scenario Tests


© Applied Materials, Inc.2008.
    All rights reserved.
    Legal Information